What plots really change hands for
Our own record of the DHA market: the asking price, the price it most likely closed at, and how long the block took to absorb it
Last updated: 27 October 2026
Read this first — what is counted and what is estimated
No dealer in DHA tells anyone the price a plot actually changed hands at. So this page does not pretend to know it. What it does know is real: when a listing stops being re-posted for 30 days it has left the market, and we have the day it first appeared and the day it was last seen — so the number of DAYS is a counted fact. The PRICE column marked in green is an estimate: 5–10% under the asking demand, which is the same rule the plot-value tool uses and comes from the office's own experience. In DHA a deal does not close above the asking; the demand is the ceiling and the bargaining happens beneath it.
No dealer in DHA tells anyone the price a plot actually changed hands at. So this page does not pretend to know it. What it does know is real: when a listing stops being re-posted for 30 days it has left the market, and we have the day it first appeared and the day it was last seen — so the number of DAYS is a counted fact. The PRICE column marked in green is an estimate: 5–10% under the asking demand, which is the same rule the plot-value tool uses and comes from the office's own experience. In DHA a deal does not close above the asking; the demand is the ceiling and the bargaining happens beneath it.
Plots gone
17,042
since our record began
Time to go (median)
16 days
from 12,002 watched
Gone within 30 days
65%
real count
Came back
3,057
the deal fell through
1,820 plots match · 1 Kanal
| Plot | Was asking | Likely deal (estimate) | Lakh/marla | Days | Last seen |
|---|---|---|---|---|---|
| U-1566/11 Phase 7 · 1 Kanal | 4.25 crore | 3.83 crore – 4.04 crore | 21.3 | 191 | 2026-09-18 came back 1× |
| M-437 Phase 9 Prism · 1 Kanal | 3.05 crore | 2.75 crore – 2.90 crore | 15.3 | 32 | 2026-09-18 |
| Q-300 Phase 9 Prism · 1 Kanal | 3 crore | 2.70 crore – 2.85 crore | 15 | 285 | 2026-09-18 came back 1× |
| C-739 Phase 9 Prism · 1 Kanal | 2.90 crore | 2.61 crore – 2.76 crore | 14.5 | 62 | 2026-09-18 |
| Z1-302 Phase 8 · 1 Kanal | 2.65 crore | 2.39 crore – 2.52 crore | 13.3 | 284 | 2026-09-18 came back 1× |
| H-1240 Phase 9 Prism · 1 Kanal | 2.60 crore | 2.34 crore – 2.47 crore | 13 | 127 | 2026-09-18 |
| N-255 Phase 9 Prism · 1 Kanal | 2.35 crore | 2.12 crore – 2.23 crore | 11.8 | 171 | 2026-09-18 came back 1× |
| K-618 Phase 6 · 1 Kanal | 7.80 crore | 7.02 crore – 7.41 crore | 39 | 86 | 2026-09-17 came back 1× |
| W-1340 Phase 7 · 1 Kanal | 5.75 crore | 5.18 crore – 5.46 crore | 28.8 | 64 | 2026-09-17 |
| N-732 Phase 6 · 1 Kanal | 5.65 crore | 5.09 crore – 5.37 crore | 28.3 | 279 | 2026-09-17 came back 1× |
| T-2418 Phase 7 · 1 Kanal · ★ | 5.50 crore | 4.95 crore – 5.23 crore | 27.5 | 52 | 2026-09-17 |
| AA-57 Phase 4 · 1 Kanal | 5.10 crore | 4.59 crore – 4.85 crore | 25.5 | 275 | 2026-09-17 came back 1× |
| H-355 Phase 9 Prism · 1 Kanal | 3.65 crore | 3.29 crore – 3.47 crore | 18.3 | 41 | 2026-09-17 |
| A-327 Phase 9 Prism · 1 Kanal | 3.55 crore | 3.20 crore – 3.37 crore | 17.8 | 284 | 2026-09-17 |
| F-294 Phase 9 Prism · 1 Kanal | 3.55 crore | 3.20 crore – 3.37 crore | 17.8 | 78 | 2026-09-17 came back 2× |
| H-1241 Phase 9 Prism · 1 Kanal | 2.65 crore | 2.39 crore – 2.52 crore | 13.3 | 17 | 2026-09-17 |
| C-1344 Phase 9 Prism · 1 Kanal | 2.60 crore | 2.34 crore – 2.47 crore | 13 | 67 | 2026-09-17 came back 1× |
| C-1187 Phase 9 Prism · 1 Kanal | 2.60 crore | 2.34 crore – 2.47 crore | 13 | 31 | 2026-09-17 |
| C-171 Phase 8 · 1 Kanal · ★ | 18.50 crore | 16.65 crore – 17.58 crore | 92.5 | 41 | 2026-09-16 came back 1× |
| C-125 Phase 8 · 1 Kanal | 18.50 crore | 16.65 crore – 17.58 crore | 92.5 | 163 | 2026-09-16 came back 1× |
| L-321 Phase 6 · 1 Kanal | 7.60 crore | 6.84 crore – 7.22 crore | 38 | 14 | 2026-09-16 |
| G-100 Phase 6 · 1 Kanal | 7.25 crore | 6.53 crore – 6.89 crore | 36.3 | 281 | 2026-09-16 came back 1× |
| S-24 Phase 8 · 1 Kanal | 6.40 crore | 5.76 crore – 6.08 crore | 32 | 62 | 2026-09-16 came back 1× |
| Y-495 Phase 7 · 1 Kanal | 5.85 crore | 5.27 crore – 5.56 crore | 29.3 | 5 | 2026-09-16 |
| X-423 Phase 7 · 1 Kanal | 5.25 crore | 4.73 crore – 4.99 crore | 26.3 | 131 | 2026-09-16 came back 1× |
| T-370 Phase 7 · 1 Kanal | 5.10 crore | 4.59 crore – 4.85 crore | 25.5 | 12 | 2026-09-16 |
| T-820 Phase 8 · 1 Kanal · ★ | 4.75 crore | 4.28 crore – 4.51 crore | 23.8 | 75 | 2026-09-16 came back 1× |
| Q-4 Phase 9 Prism · 1 Kanal | 4.55 crore | 4.10 crore – 4.32 crore | 22.8 | 281 | 2026-09-16 came back 1× |
| Y-1382 Phase 7 · 1 Kanal | 4.55 crore | 4.10 crore – 4.32 crore | 22.8 | 34 | 2026-09-16 |
| W-1405 Phase 7 · 1 Kanal | 4.50 crore | 4.05 crore – 4.28 crore | 22.5 | 21 | 2026-09-16 |
| Q-900 Phase 9 Prism · 1 Kanal | 4.30 crore | 3.87 crore – 4.09 crore | 21.5 | 8 | 2026-09-16 |
| T-2477 Phase 7 · 1 Kanal · ★ | 4.25 crore | 3.83 crore – 4.04 crore | 21.3 | 86 | 2026-09-16 came back 2× |
| N-1123 Phase 9 Prism · 1 Kanal | 3.70 crore | 3.33 crore – 3.52 crore | 18.5 | 128 | 2026-09-16 |
| T-1026 Phase 7 · 1 Kanal · ★ | 3.55 crore | 3.20 crore – 3.37 crore | 17.8 | 380 | 2026-09-16 came back 1× |
| M-120 Phase 9 Prism · 1 Kanal | 3.30 crore | 2.97 crore – 3.14 crore | 16.5 | 267 | 2026-09-16 came back 2× |
| K-373 Phase 9 Prism · 1 Kanal | 2.70 crore | 2.43 crore – 2.57 crore | 13.5 | 51 | 2026-09-16 |
| M-914 Phase 9 Prism · 1 Kanal | 2.40 crore | 2.16 crore – 2.28 crore | 12 | 217 | 2026-09-16 came back 1× |
| L-18 Phase 6 · 1 Kanal | 8.75 crore | 7.88 crore – 8.31 crore | 43.8 | 42 | 2026-09-15 |
| H-544 Phase 5 · 1 Kanal | 7.25 crore | 6.53 crore – 6.89 crore | 36.3 | 42 | 2026-09-15 |
| A-562 Phase 5 · 1 Kanal | 6.80 crore | 6.12 crore – 6.46 crore | 34 | 7 | 2026-09-15 |