What plots really change hands for

Our own record of the DHA market: the asking price, the price it most likely closed at, and how long the block took to absorb it

Last updated: 27 October 2026

Read this first — what is counted and what is estimated
No dealer in DHA tells anyone the price a plot actually changed hands at. So this page does not pretend to know it. What it does know is real: when a listing stops being re-posted for 30 days it has left the market, and we have the day it first appeared and the day it was last seen — so the number of DAYS is a counted fact. The PRICE column marked in green is an estimate: 5–10% under the asking demand, which is the same rule the plot-value tool uses and comes from the office's own experience. In DHA a deal does not close above the asking; the demand is the ceiling and the bargaining happens beneath it.
Plots gone
17,042
since our record began
Time to go (median)
16 days
from 12,002 watched
Gone within 30 days
65%
real count
Came back
3,057
the deal fell through

1,710 plots match · Phase 9 Prism

PlotWas askingLikely deal (estimate)Lakh/marlaDaysLast seen
J-2668
Phase 9 Prism · 5 Marla
73 lakh66 lakh – 69 lakh14.612026-09-22
R-3068
Phase 9 Prism · 5 Marla
1.05 crore95 lakh – 1 crore2112026-09-18
K-1281
Phase 9 Prism · 5 Marla
98 lakh88 lakh – 93 lakh19.612026-09-15
Q-90
Phase 9 Prism · 1 Kanal
3.40 crore3.06 crore – 3.23 crore1712026-09-14
J-918
Phase 9 Prism · 5 Marla
74 lakh67 lakh – 70 lakh14.812026-09-13
B-852
Phase 9 Prism · 1 Kanal
2.75 crore2.48 crore – 2.61 crore13.812026-09-11
J-2589
Phase 9 Prism · 5 Marla
76 lakh68 lakh – 72 lakh15.212026-09-09
N-210
Phase 9 Prism · 1 Kanal
2.10 crore1.89 crore – 2 crore10.512026-09-09
N-39
Phase 9 Prism · 1 Kanal
1.75 crore1.58 crore – 1.66 crore8.812026-09-08
Q-370
Phase 9 Prism · 1 Kanal
3.10 crore2.79 crore – 2.95 crore15.512026-09-08
M-347
Phase 9 Prism · 1 Kanal
3.05 crore2.75 crore – 2.90 crore15.312026-09-04
B-524
Phase 9 Prism · 1 Kanal
2.70 crore2.43 crore – 2.57 crore13.512026-09-02
A-773
Phase 9 Prism · 1 Kanal
3.80 crore3.42 crore – 3.61 crore1912026-08-24
H-1195
Phase 9 Prism · 1 Kanal
96 lakh86 lakh – 91 lakh4.812026-08-08
R-2712
Phase 9 Prism · 10 Marla
1.65 crore1.49 crore – 1.57 crore16.512026-08-07
J-686
Phase 9 Prism · 5 Marla
85 lakh77 lakh – 81 lakh1712026-08-07
L-1189
Phase 9 Prism · 10 Marla
1.78 crore1.60 crore – 1.69 crore17.812026-08-07
C-1717
Phase 9 Prism · 10 Marla
1.70 crore1.53 crore – 1.62 crore1712026-08-04
R-1792
Phase 9 Prism · 5 Marla
1.05 crore95 lakh – 1 crore2112026-08-04
M-959
Phase 9 Prism · 1 Kanal
3.20 crore2.88 crore – 3.04 crore1612026-08-04
P-475
Phase 9 Prism · 1 Kanal
2.90 crore2.61 crore – 2.76 crore14.512026-07-30
L-1355
Phase 9 Prism · 10 Marla
1.75 crore1.58 crore – 1.66 crore17.512026-07-30
K-1159
Phase 9 Prism · 5 Marla
95 lakh86 lakh – 90 lakh1912026-07-30
R-2711
Phase 9 Prism · 10 Marla
1.70 crore1.53 crore – 1.62 crore1712026-07-30
J-1844
Phase 9 Prism · 10 Marla
1.45 crore1.31 crore – 1.38 crore14.512026-07-29
C-478
Phase 9 Prism · 1 Kanal
3.15 crore2.84 crore – 2.99 crore15.812026-07-27
F-1386
Phase 9 Prism · 10 Marla
1.80 crore1.62 crore – 1.71 crore1812026-07-22
Q-1004
Phase 9 Prism · 10 Marla
2.35 crore2.12 crore – 2.23 crore23.512026-07-18
K-128/27
Phase 9 Prism · 5 Marla
90 lakh81 lakh – 86 lakh1812026-07-07
T-1439
Phase 9 Prism · 5 Marla
22 lakh20 lakh – 21 lakh4.412026-07-04
V-4680
Phase 9 Prism · 5 Marla
30 lakh27 lakh – 29 lakh612026-07-04
R-920
Phase 9 Prism · 5 Marla
1.05 crore95 lakh – 1 crore2112026-07-04
R-862
Phase 9 Prism · 5 Marla
1.05 crore95 lakh – 1 crore2112026-07-04
B-76
Phase 9 Prism · 1 Kanal
2.85 crore2.57 crore – 2.71 crore14.312026-07-03
R-2208
Phase 9 Prism · 5 Marla
1.15 crore1.04 crore – 1.09 crore2312026-07-02
A-855
Phase 9 Prism · 1 Kanal
1.40 crore1.26 crore – 1.33 crore712026-07-02
R-1469
Phase 9 Prism · 5 Marla
1 crore90 lakh – 95 lakh2012026-06-23
E-806/14
Phase 9 Prism · 5 Marla
1.26 crore1.13 crore – 1.20 crore25.212026-06-19
W-567
Phase 9 Prism · 1 Kanal
5.20 crore4.68 crore – 4.94 crore2612026-06-19
D-2177
Phase 9 Prism · 5 Marla
1.08 crore97 lakh – 1.03 crore21.612026-06-19